Appendix 10-1

Implementation Schedule of

recommended Environmental Mitigation Measures

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


EIA* Ref.

EM&A Log Ref.*

Environmental Protection Measures

Location/Duration of Measures/ Timing of Completion of Measures

Implemen-tation

Implementation Stage*

Relevant Legislation & Guidelines*

Des

C

O

Dec

 

 

Establishment Phase

 

 

 

 

 

 

 

S4.5

S4.8

Fugitive Dust Emission

·        The dust control measures required under the Air Pollution Control (Construction Dust) Regulation should be implemented. Working areas where excavation or earthmoving are taking place shall be sprayed with water or a dust suppression chemical.  Any stockpiling of excavated material shall be covered by impervious sheeting or sprayed with water or a dust suppression chemical.

 

 

All construction work areas, especially those located on the northern side of the site/ During fill bank establishment when dusty activities are carried out

Contractor

 

Ö

 

 

EIAO-TM

APC(CD)R

S4.5

S4.8

·        Erection of site hoarding of at least 2.4m high (from ground level) along the northern side of the site boundary except at the site entrance/exit location

 

Northern site boundary/ During fill bank establishment

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

APC(CD)R

S4.5

S4.8

·        Installation of vehicle wheel washing facilities including a high pressure water jet provided at designated vehicle exit points

 

Site entrance/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

APC(CD)R

S4.5

S4.8

·        Paving the designated main haul roads with concrete, bituminous materials, hardcores or metal plates

 

Main haul road/ During fill bank establishment

 

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

APC(CD)R

S4.5

S4.8

·        The machinery of the C&DMSF shall be enclosed in a shelter and equipped with proper dust filtration system (e.g. bag filters)

                  

C&DMSF/ During fill bank establishment

 

Contractor

 

Ö

 

 

EIAO-TM

APC(CD)R

S4.5

S4.8

·        The C&DMSF shall also be designed to facilitate the loading of fill material from public fill delivery trucks and with drop height minimised to no more than 1m. At the C&DMSF, the storage areas shall at least be enclosed on three sides

 

C&DMSF/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

APC(CD)R

S4.7

S4.8

·        The tipping hall for transfer of public fill from trucks to barges at the barging point shall be enclosed on top and three sides.

 

Barging Point/ During fill bank establishment

 

CED/ Contractor

Ö

 

 

Ö

EIAO-TM

APC(CD)R

 

 

 

* See Notes at End of Table for Codes

 

 

 

 

 

 

 

S5.4

S5.2

Construction Noise Impact

·        All construction works will be carried out during the non-restricted hours (i.e. 7:00 a.m. to 7 p.m. on weekdays other than general holidays)

 

All construction work areas, especially those located on the northern side of the site/ During fill bank establishment/ When noisy activities are carried out

Contractor

 

Ö

 

 

Noise Control OrdinanceEIAO-TM

PN 2/93

S5.5

S5.2

·        Before the commencement of any work that may generate a significant noise impact, the Contractor shall submit to the Engineer for approval the method of working, equipment and sound-reducing measures (e.g. use of silenced type of equipment, etc.) intended to be used

 

All construction work areas, especially those located on the northern side of the site/ During fill bank establishment/ When noisy activities are carried out

Contractor

 

Ö

 

 

EIAO-TMNoise Control Ordinance

PN 2/93

S6.4 & S6.5

S7.9

Water Quality

·        The existing drainage channels constructed at TKO Area 137 should be used and realigned to fit into the design of the fill bank

 

Existing drainage channel/ During fill bank establishment

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S. 6.5

S7.9

·        Before the complete realignment of the existing channels, earth bunds and sand bag barriers shall be used to divert flows to the existing/ realigned channel

 

All construction work areas, especially those located near the waterfront on the western and southern sides/ During fill bank establishment

 

Contractor

 

Ö

 

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S. 6.5

S7.9

·        The temporary drainage facilities provided shall allow polluted stormwater to be diverted to existing/ realigned intercepting channels before stockpiling of public fill should begin.  The intercepting channels shall be equipped with adequately designed sand/ silt removal facilities to allow the stormwater to be treated before discharge at the designated outfalls; 

 

All construction work areas, especially those located near the waterfront on the western and southern sides/ During fill bank establishment

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

PN 1/94

WPCO

S. 6.5

S7.9

·        Effluent discharge from the site during the establishment phase shall meet the relevant discharge limits specified in the Technical Memorandum on Standards for Effluent Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters; 

 

Discharge point/During fill bank establishment/ When construction activities having the potential to generate a water quality impact are carried out

Contractor

 

Ö

 

 

EIAO-TM

PN 1/94

WPCO

S. 6.5

S7.9

·        Catchpits, sand and silt removal facilities and intercepting channels provided onsite should be maintained to ensure proper functioning, and the deposited silt and grit should be removed weekly at the onset of and after each rainstorm to ensure that these facilities are functioning at all times.

 

All construction work areas/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

PN 1/94

PCO

(Cap. 358)

S7.6

S6.3

Landfill Gas/ Leachate Migration Hazard

·        The container office at the site entrance located within the SENT landfill consultation zone shall be supported by a raised hollow platform to allow passive ventilation and avoid accumulation of landfill gas beneath the structures;

 

Within the SENT Landfill consultation zone/ During fill bank establishment

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

PN 3/96

S7.6

S6.3

·        Main site offices and other site facilities having the potential to trap landfill gas shall be located outside the SENT landfill consultation zone

 

Within the SENT Landfill consultation zone/ During fill bank establishment

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

PN 3/96

S7.6

S6.3

·        No underground drainage and sewerage system including underground pipelines and chambers shall be constructed within the SENT landfill consultation zone

 

Within the SENT Landfill consultation zone/ During fill bank establishment/ When construction activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

CED/ Contractor

Ö

Ö

 

 

EIAO-TM

PN 3/96

S7.6

S6.3

·        Access by the general public to the fill bank shall be restricted

Within the fill bank/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

 

S7.8

S6.3

·        The contractor should be aware of, and should inform supervisor and workers of the risk nature and associated hazards of landfill gas including fire, explosion and toxic effect, gas detection method, health effect of leachate and contingency measures for leachate/ groundwater contamination

 

Within the fill bank/ During fill bank establishment

 

 

 

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S7.8

S6.3

·        Precautions should be clearly laid down and rigidly adhered for activities such as excavation, trenching and creation of confined or semi-confined spaces, if any, carried out within or near the SENT landfill consultation zone

 

Within the SENT Landfill consultation zone/ During fill bank establishment/ When construction activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S7.8

S6.3

·        In addition to normal site safety procedures, gas detection equipment and appropriate breathing apparatus should be available and used when entering confined spaces or trenches deeper than 2 metres;

 

Within the SENT Landfill consultation zone/ During fill bank establishment/ When construction activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S7.8

S6.1

·        A Safety Officer/ Supervisor should be present on site throughout the construction stage;

 

Within the fill bank/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S7.8

S6.1

·        The Safety Officer/ Supervisor should be provided with an intrinsically safe portable instrument(s), appropriately calibrated and capable of measuring the gases in the ranges as recommended in the EIA Report;

 

Within the fill bank/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S7.8

S6.1

·        A LFG monitoring programme should be formulated by the Safety Officer/ Supervisor or by a qualified person when construction activities are carried out.  Periodic/routine monitoring should be conducted during ground-works, in all excavations, and works at confined spaces, if any.  The action plan recommended in the EIA report should be implemented;

 

Within the SENT Landfill consultation zone/ During fill bank establishment/ When construction activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

 

 

 

 

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S7.7

S6.4

·        During the construction works for realignment of the existing drainage channels or other construction activities, should there by any sign of leachate-contaminated groundwater being encountered, the SENT landfill operation should be informed for the leachate-contaminated groundwater to be collected and transferred back to the sewage treatment works of the SENT landfill for treatment by the SENT operator;

 

Within the SENT Landfill consultation zone/ During fill bank establishment / When construction activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

Ö

 

 

EIAO-TM

PN 3/96

S2.3.4

N.A.

Other Environmental Factors

·        A 2.4m high site fencing shall be erected along the northern site boundary abutting Fat Tong Chau to avoid any accidental disturbance of the cultural heritage site by the workers

 

Along the northern boundary of the site/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

 

S2.3.3

N.A.

·        A buffer zone of at least 10m shall be provided along the eastern boundary of the site to separate the work areas of the fill bank from the eastern boundary of the adjacent Clearwater Bay Country Park

.

Along the northern and eastern boundary of the site/ During fill bank establishment

Contractor

 

Ö

 

 

EIAO-TM

 

 

 

Operational Phase

 

 

 

 

 

 

 

S4.6

S4.8

Fugitive Dust Emission

·        Works that involve the stockpiling of dusty materials are regulated under the Air Pollution Control (Construction Dust) Regulation as regulatory work.  In accordance with the requirements of the Air Pollution Control (Construction Dust) Regulation, dust control/ mitigation measures shall be implemented to ensure full protection of the nearby ASRs

 

All operational work areas / During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Working methods should be devised with consideration of the potential dust generation and dust control measures required under the Air Pollution Control (Construction Dust) Regulation and to ensure any installed air pollution control system and measures are operated and/or implemented in accordance with their design merits.  In the event of malfunctioning of any control system or equipment, the relevant dusty activities shall stop until the relevant control system or equipment are restored to proper functioning;

All operational work areas / During fill bank operation

 

 

 

 

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Frequent mist spraying should be applied on dusty areas.  The frequency of spraying required will depend upon local meteorological conditions such as rainfall, temperature, wind speed and humidity, the activity levels at the fill bank.  Mist spaying should be applied to dampen the dusty material without overwatering;

 

All operational work areas, especially those located on the northern side of the site/ During fill bank operation/ When dusty activities are carried out

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Truck drivers using the fill bank shall be checked to have a valid dumping licence.

 

All operational work areas/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

Air Pollution Control (Construction Dust) Regulation

S4.6

S4.8

·        A buffer zone of at least 100m shall be maintained between the edge of the stockpiling area and the nearest ASRs at the TKO Industrial Estate.  Within the buffer zone, no dusty material shall be stockpiled and no loading/ unloading and similar activities should be allowed.

Buffer zone/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

Air Pollution Control (Construction Dust) RegulationHKPSG

S4.6

S4.8

·        Truck speed limit shall be limited to within 10km per hour;

 

Site Haul Road/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

Air Pollution Control (Construction Dust) Regulation

S4.6

S4.8

·        Public fill delivery trucks entering/ leaving TKO Area 137 shall be required to follow a designated site main haul route that is covered with concrete, bituminous materials, hardcores or metal plates

 

Site Haul Road/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        The main haul route provided for regular transport of public fill from the barging point to the C&DMSF shall also be covered with concrete, bituminous materials, hardcores or metal plates to minimum dust emissions.  The designated haul route shall be located away from nearby ASRs

 

Site Haul Road/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Water lorries and/or road sweepers shall be provided and used in dust suppression.  Frequent watering (at least three times per day) of the haul roads is necessary.  The frequency shall be increased when the weather is dry, when the truckloads are high, and for haul roads located within 100m from the northern boundary of the site

 

Site Haul Road/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        All dusty fill material shall be sprayed with water or a dust suppression chemical prior to loading, unloading or transfer so as to maintain the fill material wet, except for situations where the moisture content of the dusty material is a matter of concern;

 

All operational work areas / During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Frequent watering (at least three times per day) of the worksites with active dusty operations. The frequency shall be increased when the weather is dry

 

All operational work areas / During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Vehicle washing facilities including high pressure water jet installed at the existing exit shall be maintained and operated by designated staff to ensure that these dust control measures are being used

 

Site entrance/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Before leaving the fill bank, every vehicle shall be washed to remove any dusty materials from its body and wheels

 

Site entrance/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Trucks carrying dusty load entered to the site shall be sprayed with water once the impervious sheeting covering the load is removed

 

Site entrance/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

Air Pollution Control (Construction Dust) Regulation

S4.6

S4.8

·        Public fill at the stockpiling area should be handled to avoid segregation, deterioration, erosion or instability of the material, especially for the stockpiling surface facing to the north of the site.  The portions of site and stockpiling height allocated and allowed by the project engineers for stockpiling of public fill shall be followed in the daily operation of the fill bank

Stockpiling area/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Temporary slope surfaces, especially those facing to the north of the site, shall either be covered with tarpaulin sheeting or other impermeable sheeting, or sprayed with water or a dust suppression chemical, or protected by other methods approved by CED.  Mist spaying should be apply to dampen the dusty material without over-watering

Stockpiling area/ During fill bank operation

 

 

 

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Final slope surfaces, especially those facing to the north of the site, shall be treated by compaction, followed by hydroseeding, vegetation planting or sealing with shotconcrete, latex, vinyl, bitumen, or other suitable surface stabiliser approved by CED

 

Stockpiling area/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        When belt conveyor systems are in use for transfer of fill material, the conveyors shall be enclosed on top and 2 sides.  Every transfer point between any two conveyors shall be enclosed

 

Belt conveyer system/During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        An effective belt scraper shall be installed at the head pulley of every belt conveyor to dislodge fine particles that may adhere to the belt surface, and to reduce carrying back of fine particles on the return belt

 

Belt conveyer system/During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        The belt scraper shall be equipped with bottom plates or other similar means to prevent falling of material from the return belt

 

Belt conveyer system/During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        The level of stockpiling belt conveyor shall be adjustable such that the vertical distance between the belt conveyor and the material landing point is maintained at no more than 1m

 

Belt conveyer system/During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Dusty material loaded from a belt conveyor outlet to stockpiles, storage bins, trucks, barges and other open areas shall be sprayed with water or a dust suppression chemical

 

Belt conveyer system/During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S4.6

S4.8

·        Loading of dusty material delivered by barges to the site shall be sprayed with water at the material landing point.  At the C&DMSF, the loading of material shall be sprayed with water to minimise dust emission.

 

 

 

 

C&DMSF & Barging point/During fill bank operation

 

 

 

Contractor

 

 

Ö

 

EIAO-TM

APC(CD)R

S5.5

S5.2

Fixed Noise Impact

·        The noise standards specified in the Technical Memorandum for the Assessment of Noise From Places Other Than Domestic Premises, Public Places or Construction Sites shall be met

 

 

All operational work areas, especially those located on the northern side of the site/ During fill bank operation/ When noisy activities are carried out

Contractor

 

 

Ö

 

NCO

EIAO-TM

S3.2

S5.2

·        The operating hours of the fill bank shall be restricted to 8:00 a.m. to 9:00 p.m.

 

All operational work areas / During fill bank operation

 

Contractor

 

 

Ö

 

Noise Control Ordinance

EIAO-TM

S3.2

S5.2

·        The operating hours of the barging point and the C&DMSF within the fill bank shall be restricted to 8:00 a.m. to 7:00 p.m.

 

All operational work areas / During fill bank operation

Contractor

 

 

Ö

 

Noise Control Ordinance

EIAO-TM

S5.5

S5.2

·        Before the commencement of any work that may generate a significant noise impact, the Contractor shall submit to the Engineer for approval the method of working, equipment and sound-reducing measures (e.g. use of silenced type of equipment, etc.) intended to be used

 

All operational work areas / During fill bank operation

Contractor

 

 

Ö

 

Noise Control Ordinance

EIAO-TM

S3.2, S5.1, S5.5

N.A.

Traffic Noise Impact

·        A marine based transportation route for public fill shall be provided at TKO Area 137 to allow public fill to be transported to the site from the planned barging point in the ex-Kai Tak Airport in addition to land-based access from Wan Po Road;

 

Onsite barging point; barging point at ex-Kai Tak airport barging point / During fill bank operation

 

CED/ Contractor

Ö

 

Ö

 

EIAO-TM

S3.2, S5.1, S5.5

N.A.

·        Through the existing trip-ticket system, truckloads generated from Government/ Public Corporations’ contracts using the proposed fill bank at TKO Area 137, except those generated within Tseung Kwan O, should be diverted away from Wan Po Road by using a marine-based access;

 

Wan Po Road/ During fill bank operation/ When there is public fill intake to the fill bank

 

CED/ Contractor

Ö

 

Ö

 

EIAO-TM

S5.1

N.A.

·        During the operation-decommissioning overlapping period, delivery of public fill removed from the fill bank shall all by means of barges;

Onsite barging point/ During fill bank operation

Contractor

 

 

Ö

Ö

EIAO-TM

S5.1

N.A.

·        The temporary fill bank shall not receive further public fill from January 2005.

  

All operational work areas/ During fill bank operation

 

Contractor

 

 

Ö

Ö

EIAO-TM

S6.5

S7.9

Water Quality

·        The existing/ realigned intercepting channels and the sand/ silt removal facilities should be used and maintained

 

All operational work areas, especially those located near the waterfront on the western and southern sides/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Temporary intercepting drains should be used at the stockpiling area to divert polluted stormwater to the intercepting channels. Earth bunds and sand bag barriers shall be used to assist the diversion of polluted stormwater to the intercepting channels.

 

All operational work areas, especially those located near the waterfront on the western and southern sides/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Effluent discharged from the site shall meet the relevant discharge limits specified in the Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters.

 

Discharge point/ During fill bank operation

 

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

WPCO

 

S6.5

S7.9

·        To minimise potential water quality impact associated with runoff of polluted surface water, a buffer distance of at least 100m shall be maintained between the boundary of the public fill stockpiling area and the sea front

 

Along the northern and eastern boundary of the site/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        A buffer distance of at least 20m should be maintained between the boundary of the C&DMSF and the seafront

 

Along the northern and eastern boundary of the site/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Operation of the C&DMSF shall be served by an effective stormwater intercepting system.  The buffer storage areas at the sorting facility shall be served by the drainage system for collection of runoff and removal of suspended solid before the stormwater is discharged to the sea at the designated outlets. 

C&DMSF/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

WPCO

S6.5

S7.9

·        The materials temporarily stored at the buffer area of the C&DMSF shall be minimised by transferring the public fill and C&D waste to the stockpiling area and SENT landfill especially before rainstorm, and the materials shall be properly covered when there is any chance for the materials to be washed away

 

C&DMSF/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Sorted material transported to the stockpiling area for storage should not contain unsuitable material such as organic, soluble material, dangerous or toxic material, and floatable materials (e.g. bottle, plastic bags, foam box) which could cause a potential water quality impact

Stockpiling area/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Temporary slope surfaces shall be covered as far as practicable with tarpaulin sheets or other impermeable sheeting or protected by other methods approved by CED especially when a rainstorm is imminent or forecast

Slope surface/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Final slope surfaces shall be treated by compaction, followed by hydroseeding, vegetation planting or sealing with shotconcrete, latex, vinyl, bitumen, or other suitable surface stabiliser approved by CED to prevent the washing away of stockpiled material

 

Slope surface/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Existing and newly constructed catchpits, sand and silt removal facilities and intercepting channels should be maintained, and the deposited silt and grit should be removed weekly and on a need basis especially at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times

 

All operational work areas/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

 

S6.5

S7.9

·        A wheel washing bay should be provided at the site exit and wash-water should have sand and silt settled out or removed before being discharged into storm drains

 

Site entrance/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        The section of construction road between the wheel washing bay and the public road should be paved with concrete, bituminous materials or hardcores to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.

 

Haul road/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Sewage from toilets should be discharged into a foul sewer, or chemical toilets should be provided

 

All operational work areas/ During fill bank operation

 

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94Water Pollution Control Ordinance (WPCO) (Cap. 358)

 

S6.5

S7.9

·        Should the use of chemical toilets be necessary, these should be provided by a licensed contractor, who will be responsible for disposal and maintenance of these facilities

 

All operational work areas/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Wastewater collected from canteen kitchens, including that from basins, sinks and floor drains, should be discharged into foul sewers via grease traps.  If no communal sewer can be provided, sewage generated from the workforce at the site offices shall be collected by septic tanks and regularly removed by using vacuum tankers

 

All operational work areas/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Drainage system provided at car parking areas shall be provided with oil interceptors in addition to sand/ silt removal facilities

 

All operational work areas/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        The contractor shall select barges of the right size such that adequate clearance is maintained between the vessels and the sea bed at all states of the tide to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash

 

Barging point/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

 

S6.5

S7.9

·        All vessels used for transportation of fill material should have tight fitting seals to their bottom openings to prevent leakage of material during transport

 

 

 

 

 

 

 

 

 

Barging point/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Relevant design measures including such as the following shall be specified in the Technical Specification to avoid dropping of fill material into the sea during the transfers:

(i)      When backhoe fixed on an appropriately design flat-top pontoon is in use, the reach of the backhoe shall be controlled to within the flat-top pontoon of sufficient length to avoid accidental dropping of public fill into the sea;

(ii)     When hopper barges with mobile crane is in use, guardrails or equivalent shall be fixed alongside the berthing faces to guide the movement of the crane to avoid accidental dropping of fill material into the sea;

(iii)   When derrick barges with built-in crane are in use, the reach of the jig shall be controlled to within the length of the barge to avoid accidental dropping of public fill into the sea

 

Barging point/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Barges should not be filled to a level which may cause the overflow of material during loading or transportation.  Barge effluents should be properly collected and treated before disposal

 

Barging point/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

WPCO

S6.5

S7.9

·        The work activities should not cause any visible foam, oil, grease, scum, litter or other objectionable matters to be present on the water in the vicinity of the barging point;

 

Barging point/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

WPCO

S6.5

S7.9

·        After the completion of the Stage 2 reclamation works in December 2003, the fill bank contractor shall be required to provide silt curtains at the outward side of the basin near the barging point throughout the operational phase when there is public fill intake by barges.  The silt curtains shall be designed such that they can also function to confine floating refuse, or separate refuse containment boom should be provided.  A waste collection vessel should be deployed to remove floating debris on the sea near the fill bank for proper disposal.

 

Barging point/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S6.5

S7.9

·        Measures detailed in the ProPECC PN 1/94 on Construction Site Drainage should be followed

All operational work areas/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 1/94WPCO (Cap.358)

S7.8

S6.3

Landfill Gas Hazard

·        The contractor should be aware of, and should inform supervisor and workers of the risk nature and associated hazards of landfill gas including fire, explosion and toxic effect, gas detection method, health effect of leachate and contingency measures for leachate/ groundwater contamination

 

 

Within the SENT Landfill consultation zone/ During fill bank operation

Contractor

 

 

Ö

 

EIAO-TM

PN 3/96

S7.8

S6.3

·        Precautions should be clearly laid down and rigidly adhered for activities such as excavation, trenching and creation of confined or semi-confined spaces, if any, carried out within or near the SENT landfill consultation zone

 

Within the SENT Landfill consultation zone/ During fill bank operation/ When activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

 

Ö

 

EIAO-TM

PN 3/96

S7.8

S6.3

·        In addition to normal site safety procedures, gas detection equipment and appropriate breathing apparatus should be available and used when workers entering confined spaces or trenches deeper than 2 metres

 

Within the SENT Landfill consultation zone/ During fill bank operation/ When activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

 

Ö

 

EIAO-TM

PN 3/96

S7.8

S6.1

·        A Safety Officer/ Supervisor should be present on site throughout the operational stage

 

Within the fill bank/ During fill bank operation

 

Contractor

 

 

Ö

 

EIAO-TM

PN 3/96

S7.8

S6.1

·        The Safety Officer/ Supervisor should be provided with intrinsically safe portable instrument(s), appropriately calibrated and capable of measuring the gases in the ranges as recommended in the EIA Report

 

 

 

Within the fill bank/ During fill bank operation

Contractor

 

 

Ö

 

PN 3/96

S7.8

S6.1

·        A LFG monitoring programme should be formulated by the Safety Officer/ Supervisor or by a qualified person when construction activities are carried out.  Periodic/routine monitoring should be conducted during ground-works, in all excavations, and works at confined spaces, if any.  The action plan recommended in the EIA report should be implemented;

 

Within the SENT Landfill consultation zone/ During fill bank operation/ When activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

 

Ö

 

EIAO-TM

PN 3/96

S7.7

S6.4

·        During the construction works for realignment of the existing drainage channels or other construction activities, should there by any sign of leachate-contaminated groundwater being encountered, the SENT landfill operation should be informed for the leachate-contaminated groundwater to be collected and transferred back to the sewage treatment works of the SENT landfill for treatment by the SENT operator

 

Within the SENT Landfill consultation zone/ During fill bank operation/ When activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

 

Contractor

 

 

Ö

 

EIAO-TM

PN 3/96

S8.12

N.A.

Landscape and Visual

·        The design of the fill bank and platform heights adopted should allow the fill bank to fit into the general topography of the surrounding land.  Straight edged slopes should be avoided

 

Stockpiling area, barging point and C&DMSF/ During the operational phase of the fill bank/ When there is public fill intake to the site and stockpiling activities

CED/ Contractor

Ö

 

 

 

 

Ö

 

EIAO-TM

S8.10

S2.2

·        The maximum stockpiling height at the fill bank shall be limited to a maximum of +35.2mPD

 

Stockpiling area / During the operational phase of the fill bank/ When there is public fill intake to the site and stockpiling activities

CED/ Contractor

Ö

 

 

 

 

Ö

 

EIAO-TM

S8.12

N.A.

·        Surface of outer slopes of the fill bank shall preferably be hydroseeded or covered with geo-textile matting of appropriate colour (e.g. dark green/ brown) once completed.  Use of coloured spray concrete should be avoided on the most visible parts of the fill bank.

 

Stockpiling area / During the operational phase of the fill bank/ When there is public fill intake to the site and stockpiling activities

 

CED/ Contractor

Ö

 

 

 

 

Ö

 

EIAO-TM

S8.12

N.A.

·        The barging point and the C&DMSF at the fill bank shall not be in operation from 7:00 p.m. to 8:00 a.m. daily to avoid potential visual impact from glare.

 

Barging point and C&DMSF/ During the operational phase of the fill bank/ When there is public fill intake to the site and stockpiling activities

CED/ Contractor

Ö

 

 

 

 

Ö

 

EIAO-TM

S2.3, S3.2

N.A.

Other Environmental Factors

·        C&D waste sorted from mixed C&D material at the C&DMSF shall be removed from the temporary buffer storage area on a daily basis and transfer to SENT landfill for disposal

C&DMSF/ During the operational phase/ When public fill that require sorted is received at the fill bank

Contractor

 

 

Ö

 

EIAO-TM

 

 

Decommissioning Phase

 

 

 

 

 

 

 

S4.6 & S4.7

S4.8

Fugitive Dust Emission

·        The dust control measures recommended for the operational phase shall continue to be applied during the decommissioning phase of the project

 

All decommissioning work areas, especially those located on the northern side of the site/ During fill bank decommissioning/ When dusty activities are carried out

Contractor

 

 

 

Ö

EIAO-TM

APC(CD)R

S4.7

S4.8

·        For excavation activities and removal of fill material, the material handled shall be sprayed with water or a dust suppression chemical before and after the operation so as to maintain the entire surface wet

 

Stockpiling area / During fill bank decommissioning/ When dusty activities are carried out

 

Contractor

 

 

 

Ö

EIAO-TM

APC(CD)R

S4.7

S4.8

·        All public fill delivery trucks leaving the fill bank shall be required to be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicles

 

Site entrance/ During fill bank decommissioning/ When dusty load is being carried by trucks

 

Contractor

 

 

 

Ö

EIAO-TM

APC(CD)R

S5.5 & S5.6

S5.2

Fixed Noise Impact

·        The noise control measures recommended for the operational phase shall continue to be applied during the decommissioning phase of the project.

 

 

 

 

All decommissioning work areas, especially those located on the northern side of the site/ During fill bank decommissioning/ When noisy activities are carried out

Contractor

 

 

 

Ö

EIAO-TM

NCO

S3.2 & S5.1

N.A.

Traffic Noise Impact

·        A marine based transportation route for public fill shall be provided at TKO Area 137 to allow at least 90% of the stockpiled public fill to be transported out of the site by barges;

 

Onsite barging point / During fill bank decommissioning/ When public fill is removed from the fill bank

CED/ Contractor

Ö

 

 

Ö

EIAO-TM

S5.1 & S5.6

N.A.

·        Dispatch rate of trucks delivering the remaining 10% stockpiled public fill off the site shall be limited to within 200 vehicles/day and 30 vehicles/hour

 

Wan Po Road/ During fill bank decommissioning/ When public fill is removed from the fill bank

 

CED/ Contractor

Ö

 

 

Ö

EIAO-TM

S6.5

S7.9

Water Quality

·        The land-based water pollution control measures recommended for the operational phase shall continue to be applied during the decommissioning phase of the project.

·        Throughout the decommissioning phase of the fill bank, a waste collection vessel should be deployed to remove floating debris on the sea near the fill bank for proper disposal.

 

 

 

All decommissioning work areas, especially those located near the waterfront on the western and southern sides/ During fill bank decommissioning/ When decommissioning activities having the potential to generate a water quality impact are carried out

Contractor

 

 

 

Ö

EIAO-TM

PN 1/94

Water Pollution Control Ordinance (WPCO) (Cap. 358)

S7.7 & S7.8

S6.1, S6.3, S6.4

Landfill Gas Hazard

·        The landfill gas migration precautionary and protection measures recommended for the operational phase shall continue to be applied during the decommissioning phase of the project

 

Within the SENT Landfill consultation zone/ During fill bank decommissioning/ When activities such as excavation, trenching and creation of confined or semi-confined spaces are carried out

Contractor

 

 

 

Ö

EIAO-TM

PN 3/96

S8.12

N.A.

Landscape and Visual

·        Stockpiled public fill should be removed in a sequence to allow the outer hydroseeded (or provided with other equivalent measures) bund slopes to be removed later than other portions subject to the engineering requirements such as stability consideration to allow the visual impact to be reduced to the shortest possible period

 

Stockpiling area / During the decommissioning phase of the fill bank/ When public fill is removed from the fill bank

CED/ Contractor

Ö

 

 

Ö

EIAO-TM

S8.12

S2.2

·        The barging point and the C&DMSF at the fill bank shall not be in operation from 7:00 p.m. to 8:00 a.m. daily to avoid potential visual impact from glare.

 

Barging point and C&DMSF/ During the decommissioning phase of the fill bank/ When public fill is removed from the fill bank

 

Contractor

 

 

 

Ö

EIAO-TM

S4.8

S4

Environmental Monitoring and Audit (During establishment, operation and decommissioning)

·        Carry out regular dust monitoring at the northern site boundary during the establishment, operation and decommissioning of the fill bank;

 

All work sites of the fill bank/ During establishment, operation and decommissioning/ when dusty activities are carried out

Carried out by the ET; checked by the IC(E)

 

Ö

Ö

Ö

EIAO-TM

S5.7

S5

·        Carry out regular auditing on implementation of noise management measures during the establishment, operation and decommissioning of the fill bank;

 

All work sites of the fill bank/ During establishment, operation and decommissioning/ when noisy activities are carried out

 

Carried out by the ET; checked by the IC(E)

 

Ö

Ö

Ö

EIAO-TM

S6.8

S7

·        Carry out water quality monitoring or review existing data obtained in the ongoing water quality monitoring during the establishment, operation and decommissioning of the fill bank;

All work sites of the fill bank/ During establishment, operation and decommissioning/ when activities having a potential to generate a water quality impact is carried out

 

Carried out by the ET; checked by the IC(E)

 

Ö

Ö

Ö

EIAO-TM

S8.12

S8

·        Carry out regular audit to avoid impacts on landscape and visual resources during the operational and decommissioning phases.

All work sites of the fill bank/ During establishment, operation and decommissioning/ when activities having a potential to generate a landscape/ visual are carried out

 

 

Carried out by the ET; checked by the IC(E)

 

Ö

Ö

Ö

EIAO-TM

N.A.

S9

·        Carry out regular site inspections to audit proper implementation of the recommended environmental control/ mitigation measures by the contractor to control potential environmental impact.

 

All work sites of the fill bank/ During establishment, operation and decommissioning/ When activities having a potential to generate a significant environmental impact are carried out

Carried out by the ET; checked by the IC(E)

 

Ö

Ö

Ö

EIAO-TM

* EIA Report or EM&A Manual Section Number;

Des = Detailed Design Phase;

C = Establishment Phase;

O = Operational Phase;

Dec = Decommissioning Phase;

EIAO-TM = Technical Memorandum on Environmental Impact Assessment Process;

APC(CD)R = Air Pollution Control (Construction Dust) Regulation;

PN 2/93 = EPD Practice Note for Professional Persons (ProPECC PN 2/93) Noise from Construction Activities – Non-statutory;

PN 1/94 = EPD Practice Note for Professional Persons (ProPECC PN 1/94) Construction Site Drainage;

PN 3/96 = EPD Practice Note for Professional Persons (ProPECC PN 3/96) Landfill Gas Hazard Assessment for Developments adjacent to Landfills;

NCO = Noise Control Ordinance (Cap. 400);

WPCO = Water Pollution Control Ordinance (Cap. 358)